Project Criteria

Material Cost
Pile Cost RM 4453
Transport Cost RM 410
Joint Material/Process RM 556
Crane Activity 4500 per session
Diesel Refill RM 450 per refill
  • Pile
  • Joints
  • Crane unload
  • Diesel Refill
  • Transport
  • Operator

Addional Tweaking

Repair Cost
Delay
No of Machine
Margin

Estimated Final

RM 554,232

Estimated Cost

23 Days

Estimated Duration

RM 568,232

Esimated Total Tender Price
5% margin

RM 68,232

Estimated Profit